54 county roads evaluated 220.4 farm-to-market road miles

Top five roads needing work, based on traffic count/condition: 27.9 miles county-wide totaling $26 million in estimated cost

Worst condition roads: five roads county-wide totaling 12.9 miles at cost of $8.6 million

Alternate scenario: to insure safety, pair/repave/ restripe 92 intersections county-wide at a cost of $27 million

$61.6 million total for all categories. Detailed recommendations to follow.